Operations & Energy
Energy, permits and grid exposure by site
Iran-war spillovers, BAAJA permitting and state utility shifts translated into site-level cost and timing.
Brent
$88.40
~$9 war premium
US diesel (Gulf)
$4.12/gal
▲ 18% y/y
Permits exposed to shutdown
3
Dec 11 deadline
BAAJA pass probability
25%
▼ from 40%
Plant energy-cost & permitting tracker
| Site | Power | Gas $/MMBtu | Diesel | Permits | Grid | |
|---|---|---|---|---|---|---|
| Corpus Christi smelter (TX) | $71/MWh | $3.40 | $4.12 | 2 pending | Queue #148 | elevated |
| Savannah hub (GA) | $88/MWh | — | $4.05 | 0 | OK | watch |
| Toledo rolling mill (OH) | $79/MWh | $3.10 | $4.20 | 1 pending | OK | watch |
| Recycling Ph.2 (TX) | — | — | — | DOE grant | Deposit due Nov 12 | upside |
Relevant signals
All signals →11-0511-0511-0411-0411-04
Congress signals appropriations leverage to force Iran de-escalation
bothmediumEnergy & Iran
BAAJA permitting bill: Senate vote Nov 9, odds cut from 40% to 25%
opportunityimmediatePermitting
Federal funding runs out December 11 — shutdown risk in lame duck
riskimmediateFiscal
Democrats win Georgia PSC; first Democrat on Texas Railroad Commission since 1990
bothmediumState regulation
33 of 34 anti-data-center ballot initiatives succeed
bothstrategicState regulation
Business exposure
Corpus Christi smelter
Site · Texas · Power price, ERCOT, Permits
€22m
elevatedSavannah distribution hub
Site · Georgia · PSC rate case
€3m
watchRecycling expansion (Phase 2)
Project · Texas · BAAJA, Interconnection, DOE grant
€9m
upsideGulf Coast energy & diesel
Market · Gulf Coast · Iran war, Hormuz
€11m
elevatedDecisions linked to this area
Decision log →Extend US energy & diesel hedge cover to 70% for H1 2027
PendingCFO · due 15 Nov 2026 · €11m volatility
Go / hold on Recycling Phase 2 interconnection deposit
PendingCOO · due 12 Nov 2026 · €9m EBITDA timing
Shutdown contingency: accelerate customs & permit filings
In reviewCOO · due 01 Dec 2026 · €6m
Actions in progress
Prepare go/hold memo after Nov 9 voteNot started
Projects — M. Chen · due 10 Nov 2026
File early for 3 federal permitsIn progress
Site HSE — D. Ruiz · due 30 Nov 2026