Permitting · 05 Nov 2026 · Senate calendar, analyst estimates

BAAJA permitting bill: Senate vote Nov 9, odds cut from 40% to 25%

Bill would reshape timelines for transmission, generation and mining; modelling shows ~3x transmission buildout and 3.5–7% power-system savings.

opportunityimmediateconf. 75%

1 · What happened — evidence

  • ▸Cloture vote scheduled Nov 9
  • ▸Two swing senators undecided
  • ▸Probability estimate revised post-election

2 · Why it matters to us

Determines interconnection timing for Corpus Christi recycling expansion and power cost outlook for Texas site.

Key question · Does it delay a permit, capex decision or customer project?

3 · Financial / operational impact

Interconnection delay of 12 months defers ~€9m EBITDA from recycling project.

Route to
COOCEOOperations & EnergyExecutive

4 · Affected exposures

5 · Scenario effects

6 · Decisions & actions

Go / hold on Recycling Phase 2 interconnection deposit
COO · due 12 Nov 2026 · Pending
Prepare go/hold memo after Nov 9 vote0%